Started this project a few weeks ago. It's slowly moving along.
I started with this empty area next to the staircase.
Removed the drywalls and did some electrical work.
Installing the vapor barrier. To help lower the humidity in the rest of the house. (a dehumidifier will run 24/7 in this room)
New walls are taking form.
Drywalls are up. I used drywall that is resistant to humidity.
This is the outside of the room with the new wall completed and the door installed.
This weekend we built a box around the ventilation docks and did the drywall for that. We also installed 4 new ceiling lights with switches)
Next step is plastering and painting. Then I'll have to install the suspended ceiling.
After that I will finally be able to start building the pond in there.
More pics to come!
I started with this empty area next to the staircase.
Removed the drywalls and did some electrical work.
Installing the vapor barrier. To help lower the humidity in the rest of the house. (a dehumidifier will run 24/7 in this room)
New walls are taking form.
Drywalls are up. I used drywall that is resistant to humidity.
This is the outside of the room with the new wall completed and the door installed.
This weekend we built a box around the ventilation docks and did the drywall for that. We also installed 4 new ceiling lights with switches)
Next step is plastering and painting. Then I'll have to install the suspended ceiling.
After that I will finally be able to start building the pond in there.
More pics to come!